Issue - meetings

21 May 2019 - Procurement - Award of Contracts for Works, Goods and Services

Meeting: 21/05/2019 - Cabinet (Resources) Panel (Item 10)

21 May 2019 - Procurement - Award of Contracts for Works, Goods and Services

[To approve the award of contacts for works, goods and services]

Decision:

1.       That authority be delegated to the Cabinet Member for City Environment, in consultation with the Deputy Managing Director, to approve the award of a contract for Provision of Transport Services when the evaluation process is complete.

 

2.       That the contract for Tettenhall Park Paddling Pool refurbishment be awarded to William Gough and Sons Limited, of Tudor House, Moseley Road, Bilston, Wolverhampton, WV14 6JD as main contractor with Ustigate Waterplay of 11 Masthead, Capstan Court, Crossways Business Park, Dartford, DA2 6QG as sub-contractor for a duration of three months enabling completion in Summer 2019.

 

3.       That authority be delegated to the Cabinet Member for City Economy, in consultation with the Director for Regeneration, to approve the award of a contract for Civic Halls Project Management and Design when the scope and pricing is complete.

 

4.       That the Director of Governance and staff with appropriate delegated authority be authorised toexecute contracts in respect of the above as required.

Minutes:

The Panel considered proposals for the award of contracts for works, goods and services.

 

Resolved:

1.     That authority be delegated to the Cabinet Member for City Environment, in consultation with the Deputy Managing Director, to approve the award of a contract for Provision of Transport Services when the evaluation process is complete.

 

2.     That the contract for Tettenhall Park Paddling Pool refurbishment be awarded to William Gough and Sons Limited, of Tudor House, Moseley Road, Bilston, Wolverhampton, WV14 6JD as main contractor with Ustigate Waterplay of 11 Masthead, Capstan Court, Crossways Business Park, Dartford, DA2 6QG as sub-contractor for a duration of three months enabling completion in Summer 2019.

 

3.     That authority be delegated to the Cabinet Member for City Economy, in consultation with the Director for Regeneration, to approve the award of a contract for Civic Halls Project Management and Design when the scope and pricing is complete.

 

4.     That the Director of Governance and staff with appropriate delegated authority be authorised toexecute contracts in respect of the above as required.